CRYOINFRA – COATZACOALCOS – MEXICO

Cryoinfra

DESCRIPTION: Design and construction of a chilled water production plant formed by two absorptionchillers actuated by steam. The steam is provided by a combined cycle plant situated in the surroundings ofthe production plant to maximize the efficiency of the system. COOLING PRODUCTION (32 – 57 °F) 2 x absorption chillers 6,720 RT 4 x cooling […]

SANGSTER INTERNATIONAL AIRPORT – JAMAICA

Aeropuerto de Sangster

New chiller installation and HVAC system upgrade Two new air-cooled screw chillers (490 TR each) to feed all existing units at the Main (West) Terminal. Integration of new chillers and pumps to the existing building management system.   Construction of new Fire Hall Construction of buildings and outdoor area. Installations (plumbing, fire protection, electricity, communications, […]

CALI INTERNATIONAL AIRPORT AND TOLEMAIDA AIRBASE – COLOMBIA

Aeropuerto de cali

CALI INTERNATIONAL AIRPORT Adequacy of lighting according to ICAO Implementation of LED technology. Runway visual aids, approach and taxiway lights, guidance signs, windsocks and CCR. Replacement of primary and secondary cable. Replacement of masts / lighting superpoles.   TOLEMAIDA AIRBASE Runway resurfacing 04L-22R Supply, installation and commissioning of visual aids.

TRIGENERATION DATA CENTER – ALESTRA

Trigeneracion Alestra

DESCRIPTION: Refurbishment, redesign, commissioning and O&M of the trigeneration plant using natural gas engines for electricity generation. The plant provides cooling energy to control the temperature of the Data Center server room. High system reliability is required to continuously supply the cooling demand. The plant has the capacity to work as an island in critical […]

COSTA DEL SOL AIRPORT – SPAIN

Aeropuerto costa del sol

VISUAL AIDS AND NAVIGATION Track 12-30 CAT III and associated tracks. Low Voltage installation maintenance. Regeneration of pavement on Runway 13-31. New Radar Station and Communications Center.   TERMINALS AND BUILDINGS Reuse of water in the Thermofrigorific Plant. Data Processing Center Facilities. Access control system to the new parking building.

GRANJAS CARROLL BIOGAS – MEXICO

Carrgol Biogas

DESCRIPTION: Design and construction of two power generation plants with biogas combustion engine generators. The biogas is generated in the same farm achieving an efficient and renewable solution. ELECTRICITY PRODUCTION 1 x 250 kWe biogas Jenbacher combustion engine generator 1 x 988 kWe biogas Jenbacher combustion engine generator

SIGMA – MEXICO

Sigma Atitalaquia

DESCRPTION: Refurbishment of the island cogeneration plant in Atitalaquia, State of Hidalgo. High fuel efficiency, reduced carbon footprint and economic savings for Sigma. 3 MTU natural gas generator sets: 2,991 kWe. New boiler for flue gas recovery and steam production New plate heat exchangers for engine hot water utilization.

DC1 QUERÉTARO OPERATION AND MAINTENANCE

datacenter alestra

ALESTRA   MANAGEMENT OF THE COMBINED HEATING AND POWER PLANT THAT FEEDS THE DATA CENTER: Electromecanical maintenance. Operation. Optimization. Assessment.   DATA HALL INTEGRAL MAINTENANCE: Preventive. Corrective. 24×7 presence.

TOCUMEN INTERNATIONAL AIRPORT – PANAMA

Aeropuerto internacional de Tocumen

DESCRIPCIÓN: Emergency generation plan to power the airport in case of grid failure. Designed to ensure the continuous suppy of electricity to the new Airport Terminal. ELECTRICITY PRODUCTION 7 x 3,250 kWe MTU diesel engine-generators on standby: 22.750kWe.   BACKUP GENERATION PLANT 5 new generator sets of 15 MVA total.   RUNWAY “H” AND 03L […]

EL PORTILLO BAHÍA PRÍNCIPE HOTEL & RESORT – DOMINICAN REPUBLIC

El portillo Bahia Principe

DESCRIPTION:Trigeneration plant “in island” comprising a natural gas motor with heat recovery to produce DHW and climatization through absorption to fulfil the hotel’s demand. ELECTRICITY PRODUCTION 1 x 850 kWe natural gas Jenbacher motor. 2 x 900 kWe diesel Cummins motors. GENERACIÓN TOTAL ELECTRICIDAD: 2.650 kWe. HEAT PRODUCTION (HOT WATER 140 °F) 4 x heat […]