Installation of electrical connection to vessels and maintenance of the installation at the pier.
DESCRIPTION: 20 kV service connection from the public grid (including Delivery
Center).
OPS Substation:
- Capacity for 2 vessels of 5 MW (supply 6.6 kV – 60 Hz).
- Capacity for 1 vessel of 7.5 MW (6.6 kV – 60 Hz supply).
Connections to vessels:
- 2 mobile connection systems with 100 m of travel along the seawall.