2024
Muelle Grande Puerto de Las Palmas de Gran Canaria

Power supply to cold ironing vessels.

DESCRIPTION: 20 kV service connection from the public grid (including Delivery
Center).

OPS Substation:

  • 1 MW capacity for 400 V – 50 Hz supply.
  • 1 MW capacity for 400 V – 60 Hz supply.

 

Connections to vessels:

  • 6 junction boxes with 1 outlet (400 V – 50/60 Hz).
  • 1 junction box with 2 outlets (400 V – 50/60 Hz).
Grande Pier, Las Palmas de Gran Canaria