1.000M2 DATA CENTER EXPANSION – INTERXION

interxion 1000 datacenterinterxion 1000 datacenter

INTERXION

 

  • Completion time: 4 months.
  • 200 workers on site.
  • Civil Works.
  • Fire Fighting Systems.
  • Safety and Security.
  • Generating sets: 2x 1.600 kVA.
  • UPS: 2x 600 kVA.
  • Enclosed busbars: 200 m – 4.000 A.
  • Power transformers: 3x 1.600 kVA.
  • Okken switchgear: 5.000 A, 85 kA.
  • Secondary switchgears: 25 ud.
  • Power wires: 40.000 m.
  • Climate control : CRACs 17x 110 kW.
Interxion Madrid